The Chartered Quality Institute

Qualityworld

1989Design competition for T5 is won by Richard Rogers Partnership
BAA submits a planning applications1993
1995T5 public enquiry begins
T5 public enquiry finishes1999
2001Temporary works and archaeology takes place and construction begins
Secretary of state for transport grants planning consent2002
2003JulyA full size section of the T5 roof is erected in Yorkshire to 'prove' the construction and erection process off the construction critical path
A full scale section of the T5 baggage system is constructed and testedAugust
NovemberWork begins on the steel superstructure of the main terminal building
The first of two rivers running through the T5 site is diverted around the airport perimeterFebruary2004  
MarchThe Piccadilly line extension westbound tunnel is finished ten days early
The first of T5's six 2,500 tonne roof sections is 'strand-jacked' into positionApril  
JulyThe main power source to the new terminal development is switched on
The 900 tonne visual control room of the new air traffic control tower is successfully moved two kilometres across Heathrow's airfieldOctober  
2005JanuaryConstruction of the satellite terminal is 65 percent complete
The T5 project hits the half way mark with 22 million man-hours workedFebruary  
AprilThe new air traffic control tower is topped out
The new Airbus A380 superjumbo overnights at Terminal 5 on it s first visit to the northern hemisphere for compatibility tests at HeathrowMay2006  
NovemberT5B, the satellite terminal, is virtually complete
The new air traffic control tower becomes operationalApril2007  
MayThe big clean of the terminal's steel work and glass facades begins

Back to main article